Since the last update in late August, the bed has been graded and shaped, drainage has been installed, and the pea stone and mix profiles have been installed. The final steps are laying the teeing surface sod, installing irrigation, and laying the tee bank sod.
The conditions have been wet, then dry, cold and then warm throughout this process which makes some of these steps tough to complete in a timely manner. The Team, which has included some guest Team members from UMGC, has done a great job adapting to these conditions!
BED PREP
DRAINAGE SYSTEM INSTALL
PEA STONE LAYER INSTALL
MIX LAYER INSTALL